How do I map a custom status to Complete, but keep it in different from Done column?

Vitalii Martyniuk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 27, 2026

The problem is following:
sprint items that have custom "On Prod" status are not considered as Completed and sprint metrics are showing these items as "In Progress". I want to map "On Prod" status to Complete. I cannot simply map via Settings -> Layout -> Columns, because they will disappear from the board or mix with tons of items in "Done" status.

Are there any solutions to keep "On Prod" items on board, but still calculate their values (story points) towards the Complete metric?
image.png

3 answers

0 votes
Shalini Pradhan
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 28, 2026

Hello @Vitalii Martyniuk ,

Good day! Welcome to Atlassian Community :)

You can reorder your board columns so the rightmost column contains both "Done" and "On Prod" statuses, then rename that column to something like "Complete.". Then both status will count in sprint completion metrics.

 

0 votes
Ignacio Vera
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 28, 2026

Hi @Vitalii Martyniuk 

you can actually map more than one status to the same column.

Just drag "On Prod" into it alongside the Done status. Both will live in the same column, and once you change the status category of "On Prod" to Done in the workflow, it will count towards sprint completion as well.

0 votes
Tomislav Tobijas
Community Champion
April 28, 2026

Hi @Vitalii Martyniuk ,

Not sure if there's a workaround for this, but so far, only the far right column is considered as 'completed' status when it comes to sprints, reports, etc.

There's this feature request JRACLOUD-90410: Update Report Logic where 'Done' is based on a status category or workflow, which points more to reports, but it also captures part of what you're looking for 👀

As per official docs and articles such as this one, Atlassian recommends:

...Map all statuses that represent completed work to the rightmost column...

You could maybe build board quick filters or swimlanes that would actually 'decuple' "Done" and "On-prod" statuses 🤔

Cheers,
Tobi