How do I load story points to my sprint stories?
What I found online was to do the following steps:
Click on Jira icon >
Go to Jira Settings >
Go to Issues>
Go to Custom Fields >
Search Story Point > Click on Three Dots (right side of the Story Point)>
Click on Configuration>Click on Edit Configuration>
select an Issue Type(Story/Task/Subtask)>click on ‘Modify‘ button.
But I could not find the custom fields.
Hi @William Thompson welcome to the Atlassian community.
Steps to load the story points on a Jira issue:
In step 3, the guide means that you should go to the "Issues" tab under "Jira Settings"! (It does NOT mean the "Issues" drop-down menu in the top.)
That's the interface where you configure custom fields, workflows, etc.