How do I import work from other spaces into the top level planning template?

Faustina Eadie
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 28, 2026

I have used Plan Settings , Work in your plan and added other spaces and boards to the top level plan. It correctly shows as 600 work items but on the plan page, I cannot see the Epic and work items from the spaces added. 

2 answers

0 votes
Marc -Devoteam-
Community Champion
January 28, 2026

Hi @Faustina Eadie 

Welcome to the community.

How is your hierarchy set, are any filters applied and do you have access to all work items from all individual spaces?

0 votes
Staffan Redelius
Community Champion
January 28, 2026

Hi @Faustina Eadie and welcome!

If you have added the spaces under board settings you should be able to see the work in the Timeline. 

Additional things to check:

  • Do you have any filters applied to your timeline (check the hierarchy filter)
  • Do you have access to the spaces you have added to the plan?

Let me know if this helps!

/Staffan