How do I give a team member permissions to start/stop/edit a Sprint?

Jessica Johnston
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 11, 2024

I've been trying to give one of my team members permission to complete a Sprint while I'm OOO. I've given her admin permissions, and I even added her to the project settings. But she doesn't see the "Complete" button. I've checked this help article, but the screenshots seem out-dated, since I'm not able to replicate the same view. I'm not sure what I'm doing wrong.

1 answer

1 accepted

0 votes
Answer accepted
Joseph Chung Yin
Community Champion
January 11, 2024

@Jessica Johnston -

Hi Jessica:

The key is associated to each Jira project's permission scheme configuration for the "Manage Sprint" permission.  Each SCRUM board can pull content from one or more projects, thus for anyone who needs to manage sprints (start/stop/complete/edit), then he/she will need to granted with the rights to Manage Sprint for all the involving project(s).

The Jira admins will need update project's permission scheme to incorporate the changes for you.

Hope this helps.

Best, Joseph Chung Yin

Jira/JSM Functional Lead, Global Technology Applications Team

Viasat Inc.

Jessica Johnston
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 11, 2024

Thank you, I was able to find my Jira admin to help me do this!