How do I get my MS Project 2010 data into Jira?

James Johnson
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 28, 2012

I have several large projects that we are well into. My CIO wants us to convert everything into Jira. How do I get things like duration, start dates, finish dates, resource names, % work complete, etc. into Jira without having to manually key it in? Then how do I keep it updated from my MS Project?

3 answers

1 vote
MatthewC
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 1, 2012

The only other solution that may be worth trying is Ceptah Bridge ( http://www.ceptah.com/Bridge/Bridge.aspx )

I would NOT recommend doing repeated round trip CSV export/imports in & out of Jira/MS Project if you value your sanity! Why not manage it from within Jira using a combination of GreenHopper & one of the Gantt chart plugins? The one from jplugs in quite good https://www.jplugs.com/jacrm/

Jira isn't MS-Project but it can do a lot & the bridge is good but it's a bit slow and it won't be seemless.

1 vote
James Johnson
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 1, 2012

Thanks Kapil. I do have the Connector Plugin. It does import information to Jira, but does not allow me the control I need to export information from MS Project TO Jira. The CSV idea was a good one, but I can't figure out how to export a CSV file FROM Jira. I would like to have the column headings (field ids) so that I can correctly map my Project fields to Jira. Got any ideas?

1 vote
Kapil Bolli
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 29, 2012

Hello Tninie,

We can keep a synch between MSproject & JIRa using the Connector Plugin.

Please check the below link:https://plugins.atlassian.com/plugins/com.ecliptictech.connector

Also if you want to import data into Jira, you need to convert fata in CSV format & then import data in JIRA :

http://confluence.atlassian.com/display/JIRA/Importing+Data+From+CSV

Hope this helps you.

Regards

Kapil

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team '25, conference, certifications, bootcamps, training experience, anaheim ca,

Want to make the most of Team ‘25?

Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.

Learn more
AUG Leaders

Upcoming Jira Events