I would like to add hourly capacity for a team allocated to a project
Coming to this late, but the two questions in this thread that never got answered are the important ones, and they're still worth answering for anyone finding this.
"We do not do sprints — how do I get capacity on non-agile projects?"
Plans allocates capacity per iteration. On a scrum board that's a sprint. If your team doesn't run sprints, there's no bucket for the capacity to attach to, which is why the field never appears no matter how the team is configured. The kanban suggestion doesn't really close this — you can put kanban work in a Plan, but you're back to capacity with nothing to allocate it against.
The native workaround is to manufacture time buckets. Use fixVersions as your periods (a version per month or per week) and treat each one as a planning bucket, then sum Original Estimate per assignee per version with a filter. It's crude, it's manual, and you'll maintain it by hand — but it's free and it gets a flow team a per-period supply-versus-demand number.
"Or even better, individual capacity?"
This one has a firm answer: Plans doesn't do it, on any tier. Capacity in Plans is team-level by design — the reasoning being that agile commitments belong to the team, not the person. That's a defensible philosophy and a real gap for anyone whose team has specialists, part-timers, or people split across projects.
The gap matters more than it sounds. A team rollup can show comfortable headroom while two people on it are badly over-committed, because the average absorbs them. And someone allocated half-time to two projects reads as fine on both plans, since neither one sees the other half. There's no native view that sums a person across projects.
If you go looking for an app for either of these, three questions to ask, because they're what separate the tools:
Disclosure: I build a Jira app in this space — MassMod Agile Tools for Jira, free up to 10 users — which does per-person cross-project capacity with scrum, weekly, and monthly cadence lanes on one timeline. The fixVersion workaround above is genuinely worth trying first if you only need one team's numbers.
Not sure if it can be achieved with JWM. Other options could be using Advanced Roadmaps or an app. There are multiple marketplace apps for capacity planning
https://marketplace.atlassian.com/search?hosting=cloud&product=jira&query=capacity
We have also built an app for the same use case.
The app allows to store the capacity for individual users and save as templates. which can be mapped to a sprint to track the allocation and remaining time per user. Do try it out.
Disclaimer : I am part of the team which developed this app
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you referring to Advanced Roadmaps? As far as I am aware, work management projects don't have any sort of team or team capacity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kian Stack Mumo Systems . Ok. Can perhaps advise which project types does?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kian Stack Mumo Systems or even better, individual capacity?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
"Project types" do not. But you can create advanced roadmap plans with teams tied to them. Each team can have a capacity them.
https://support.atlassian.com/jira-software-cloud/docs/create-and-add-teams-in-advanced-roadmaps/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kian Stack Mumo Systems Advanced Roadmaps seems to require Agile process with Sprint set ups. We do not do sprints.
How can I get capacity in the system on non-agile projects?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You do not need to use sprints. You can use Kanban style work management as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kian Stack Mumo Systems I added a project to a board, but still not able to add capacity of a team. Can you perhaps advise how I go about doing this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Anneliese Pretorius, you added a project to a board, or to a roadmap? Roadmaps are located under "Plans" in the upper menu bar of your Jira instance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kian Stack Mumo Systems Added the project to a board (team linked). Board then added to a plan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I do not have the options to create a "team only" plan. Under Plan - Create Plan, I get this screen.
Under Create Team, I get this:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
A shared team will work just as well, you don't need to worry about if it is plan only team or not.
Thanks,
Kian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kian Stack Mumo Systems There is still no available field for capacity though!?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You are creating a team in the wrong way.