How do I add multiple sub task types with different workflows?

Michael Wirtz May 24, 2022

I'm trying to add multiple sub tasks with different workflows, but all i see is create subtask and when i go to issue types and add issue type I can't seem to add another sub type task

2 answers

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 26, 2022

Take a look at the project type at the bottom left of the project displays - does it say "team managed" or "company managed"?

Michael Wirtz May 26, 2022

team-managed project

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 26, 2022

Ah, that's it then.

TMPs only allow for one sub-task, there's no multiple sub-task types.

Like John Funk likes this
Michael Wirtz May 26, 2022

ah okay 

0 votes
John Funk
Community Champion
May 24, 2022

Hi Michael - Welcome to the Atlassian Community!

You will need to be a Jira Administrator, but go to Settings > Issues > Sub-tasks.

There you can add a new Sub-task type. 

Michael Wirtz May 26, 2022

I tried to do that, but when I go to my project settings, I still can only see the one sub-task.

John Funk
Community Champion
May 27, 2022

It's as Nic said - since it is a Team-managed project, there is only one Sub-task type available. 