I am having difficulty to find task from past sprints as sprint view (done tasks in each sprint). Is there a way to get that information ?
Hello @Vaidehi Rayate
Welcome to the Atlassian community.
When you are viewing a board there will be a Reports option in the panel on the left. From there you can select the Sprint Burndown Chart report (in a Team Managed project) or the Sprint Report (in a Company Managed project). Each report allows you to select the sprint you want to view, and that will show you the issues completed in the selected sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.