I have sub-tasks in the story, and I want them to be displayed as separate cards in the Kanban Board. Right now I can only see them in the story but not on the Kanban Board.
Hello @Simranjit Singh
Welcome to the Atlassian Community!
Are you working with a Team Managed project or a Company Managed project? That information can be found at the bottom of the navigation panel on the left.
If you are working with a Team Managed project you will be able to see the individual subtasks only if you set the Group By option to Subtask