Hi everyone,
Can anyone help me with rune multiple active sprints in Jira.
Is it possible to have multiple active sprints running simultaneously on the same Scrum board?
If yes, could someone please provide the step-by-step process to enable and manage parallel sprints? It would be helpful if you could also mention any prerequisites, required permissions, or settings that need to be configured.
Thank you in advance for your help!
Dvipa
It is only available for Company-managed space, and your Jira admin is required to enable the parallel sprint with the steps as stated in the following document:
https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints
Thank you.
First at the project level it needs to assigned to an active sprint.
The way we do that is by using a custom query, we assign a unique label to each Jira that needs to be on this mega sprint board.
Hope this helps.