How can I populate WBS Gantt-Chart for Jira cloud version percentage done

Swapan Das
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 18, 2021

I am not able to see any changes in percentage done in WBS Gantt-Chart for Jira cloud version. It shows always 0. I need to get it resolved as soon as possible. If you can show in screen shots, step by step that will be great

1 answer

0 votes
VPN担当者
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 19, 2021

There are two ways to manage Percent Done, and I will guide you step by step. 

  1. Go to Gantt configuration at the upper right screen.
    image-20210219-074827.png

  2. Click ”Issues” > ”Edit”
    image-20210219-074931.png

  3. Then you can choose ”Use specific field” or ”Calculate with Time Tracking automatically
    image-20210219-075045.png

 

  • Use specific field (Manually enter Percent Done)
  1. If you choose “Use specific field”, you need to enter Percent Done manually by clicking and entering the value.
    image-20210219-075536.png

  2. Then the value will be reflected.
    image-20210219-075822.png


Please see the documentation below for more information.

warning Currently, Project % Done value changes only its issues status is changed to “Done”. The feature request is already raised and can be checked below:

 

 

  • Calculate with Time Tracking automatically
  1. If you choose this option, you cannot edit Percent Done manually and you have to have “Original estimate” and “Time tracking” fields on Jira.
    image-20210219-081712.png


  2. Then Percent Done will be calculated accordingly.
    image-20210219-081841.png

Please see more information from the following documentation.

All the best,
Hal