I have tickets across multiple boards / projects but all attached to one EPIC. When I run the EPIC burndown chart, it only shows the tickets and sprints associated with the EPIC board / project, but not the other tickets attached to the EPIC. How can I bring in those board / project sprints into the EPIC burndown chart?
The Epic burndown is associated to the board not the Epic (issue). You need to create a board that represents all other boards that are tracking work in the Epic.