Struggling to add various capacities for a resource pool. To apply to various estimated story and produce a capacity plan.
Are you using Advanced Roadmaps (Plans)?
- When you create a plan you have the option to specific weekly capacity of a team.
- Create a plan with some SCRUM boards
- Stories in those boards will appear on the plan
- If you already have Story Points for those stories then this estimation will be used
- Associate Teams to Boards. Plan will use this information
- Use Scheduler option
Plans will use teams, weekly capacity, story points, sprint dates and few other factors to create a plan which you can accept or modify further before applying to your projects.
Start here: https://www.atlassian.com/software/jira/guides/roadmaps/advanced-roadmaps to know more about how Advanced Roadmaps work.