How can I be notified when a project reaches a sum of logged hours bigger than the estimated?

DPereira July 7, 2022

Several of my company's projects are sold with a limit of hours contracted.

I need to be notified by e-mail when that limit is reached, meaning, when the sum of all worklogs of that project reaches a planned time which by the way, I don't know how to set. Is that possible somehow? Using an automatic rule and if so what's the query/configuration?

 

Thanks,

1 answer

0 votes
Trudy Claspill
Community Champion
July 7, 2022

Hello @DPereira 

There is no native method to specify total hours for an entire project. I have not yet found a plug-in that would add that functionality.

You can use a dashboard to show the total hours logged against issues in a project. See 

https://community.atlassian.com/t5/Marketplace-Apps-Integrations/How-to-run-a-report-for-total-hours-logged-on-a-project-since-it/qaq-p/618117

I found this post about using Jira Automation to send an alert when time spent exceeds a hard coded value. I haven't tested this.

https://community.atlassian.com/t5/Jira-questions/plugin-for-monitoring-logged-hours-in-a-project-and-send-email/qaq-p/1070325