Hello, I am managing my work schedule using a structure.
I have uploaded long-term tasks using a CSV file, but there are tasks that are being delayed due to a series of reasons.
If the due date of those tasks is postponed, is it possible to automatically push back the due dates of the subsequent tasks as well?
I am experiencing inconvenience as I have to manually edit the due dates of over 100 subsequent tasks each time one task is delayed.
Hello @혠니혠니
If one task is delayed, other tasks can be moved on the chart as well if the following conditions are met:
- tasks have the Finish-to-Start dependencies to the originally delayed task;
- the scheduling of these tasks is automatic.
Then tasks's scheduling on the chart will be adjusted according to the original tasks's due date. However, their own due dates in Jira will not be changed and their scheduling will only be present locally on the Gantt chart.
I hope this helps. If you have more questions, please reach out to us directly at our support portal and we'll get back to you shortly.
Best regards,
Stepan
Tempo (the Structure app vendor)