In JIRA Project, there are two field names as "Date Reported" which based on the Date type, and 2nd one is "FY-Q" which based on the Short Text.
The value under "FY-Q" field should automatically be updated depending on the value under "Date Reported" field. Example: The value in the "Date Reported" field is 'Nov 29, 2024', so the value under "FY-Q" field should automatically be updated to 'FY25-Q3'.
Hi @Shardul Bhisikar -- Welcome to the Atlassian Community!
The field may be set using automation rules, formatting the Date Reported field using the date / time functions to get the short text field.
https://support.atlassian.com/cloud-automation/docs/jira-smart-values-date-and-time/#Date-format---
The keys for your scenario are:
You will likely need 2-3 rules for this scenario:
To get you started on creating your rule, please refer to these documentation and example sources:
Kind regards,
Bill
Hi Shardul - Welcome to the Atlassian Community!
You could create an Automation rule based on a Field Value Changed trigger on the Date Reported field. Then use a series of IF/ELSE conditions to set the value of the FY-Q field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.
Learn more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.