Have put down due date for each task/bug on the Scrum Board, but we are not having its visibility on the Scrum Board.
Please find attached the screenshot below for reference.
Can you please provide with an insight on how to achieve this?
Have you added it to the card display in the board configuration?
Have you entered the date on the issues as well?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Thank you for the reply. The dates were entered, however the board configuration was not proper, which is now done. Its all working well now.
Thank you for your prompt reply.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.