If one project is closed in Jira, How I do for the colaborator can not adding hours in this project
Apply a new permission scheme to the project when you close it out that makes it read only. this will prevent any changes, hours, etc. from being changed on the project.
Information on Permissions can be found here: https://confluence.atlassian.com/jirasoftwareserver/permissions-overview-939938996.html
Managing project permissions can be found here:https://confluence.atlassian.com/adminjiraserver/managing-project-permissions-938847145.html