Hi Jira Team and Community Members,
I'm hoping there's an expert out there that can help me with my issue. I've done my best to provide as much detail as possible, but please ask clarifying questions if needed - any support is greatly appreciated!
----------
High-level Problem Description: I have an issue where Jira has stopped automatically populating my newly created sprint start dates based on the previously created sprint's end date and has stopped automatically populating/defaulting my sprint duration to 2-weeks.
My Jira Setup Context and Sprint Process:
How the Problem Started:
My Research and Thoughts:
Questions and Help Needed:
----------
Looking forward to any thoughts on how to tackle this going forward. Thanks!
Best,
Gino
This is expected Jira behavior.
Jira does not store a fixed sprint duration.
New sprint dates are auto-populated only when Jira detects a consistent pattern based on your last sprint’s end date + duration.
If a sprint is changed to a Custom duration (not 1/2/3/4 weeks), Jira stops carrying dates forward and new sprints will appear without dates.
When your team switched between 2-week and 4-week sprints, Jira no longer recognized a stable pattern, so it stopped auto-populating dates for new sprints.
How to restore the automatic behavior
Go back to using strict 2-week sprints for the next few cycles.
Create 1–2 future sprints manually with correct dates.
Jira typically “relearns” the cadence after 1–2 consistent iterations.
Fixed sprint duration cannot be enforced
Jira cannot lock sprint duration natively.
If strict control is needed, you can use automation reminders or a planning app like Advanced Roadmaps.
Hope this helps!
Hi @Anthony Morais thank you very much for this reply - this is great info!
I assumed what you mentioned was likely the case - there appeared to be some sort of automatic pattern recognition logic that is not exposed as explicit setting definition anywhere in the UI for users to be able to define a default sprint duration (e.g. two-weeks) as well as the start date criterion (e.g. use last created sprint's end date).
I did open a customer support ticket, and the advice I have been initially given was to copy of all my boards to create new boards within the project once my team is ready to get back into a consistent 2-week cadence after the holidays.
The logic provided around this recommendation was that Jira WILL NOT relearn sprint cadence patterns again after a few completed consistent cycles, and that I would need to create new boards to reestablish the pattern again from a fresh "zero" baseline. I believe the support representative I spoke with was not 100% sure on this, so he escalated my ticket for further review and research. I obviously do not want to have to copy my existing boards as a routine solution.
I did also ask for an enhancement request to be logged to allow users to set default settings for sprint duration and start date for the future. Hopefully that receives some visibility/traction; I've seen other users run into this exact same problem with different context.
From your advice, once my team is back on 2-week sprint cycles, and we've completed 1-2 cycles with all proactively created "on-deck" future sprints that have been adjusted manually to be two-week cycles with start dates of the previous sprint's end date, Jira SHOULD recognize a repeating pattern again, and newly created on-deck sprints SHOULD automatically populate the duration and start date to follow that pattern - correct?
Our team doesn't have a need at the moment for the core features of Advance Roadmaps, but I did see that users can control the sprint cadence more granularly with that addition.
Can you clarify what you mean by using automation reminders to help with sprint cadence control?
Thanks in advance!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gino,
Yes, you understood it correctly. Jira really depends on the pattern of previous sprints to automatically suggest the next dates. Since your team alternated between 2-week and 4-week cycles, it lost that reference, and this is expected. Once the team runs a few consecutive 2-week sprints again, Jira usually “relearns” the pattern. I’ve seen similar cases before and this is exactly what happened.
Regarding the automation reminders, what I meant was sending a notification at the end of each sprint so the team closes it on the correct date, or alerting someone when a sprint is created with an unexpected duration. This does not fix the dates automatically, but it helps prevent Jira from losing the cadence again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks again for the follow-up @Anthony Morais
Makes sense all around - I'll keep my "on-deck" sprint creation process in place with manual adjustments, and hopefully the pattern locks back in after a couple of completed two-week cycles next year. If I find the reminders useful, I'll toss those into the mix as well.
Although not ideal, having an understanding of how automatic sprint cycle definition functions is very helpful. As a product person myself, relying on underlying recognition logic seems pretty wonky/unintuitive, so hopefully we see a future enhancement that allows teams to have explicit control over how this behaves.
- Gino
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.