Gantt chart with estimated time vs final time

Fabio Polato
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 31, 2020

Hi everybody!

Is there in Jira (or in a Jira plugin) a Gantt chart with estimated time and final time for every resource?

I'm searching for something like this:

Gantt.pnghere every resource has a color and every ticket has 2 rows:

  • the first for estimate time
  • the second for final time.

I'm searching for something like this.

1 answer

1 vote
Gabriel Quadros
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 1, 2020

Hello @Fabio Polato!

My name is Gabriel Quadros and I'm from Ricksoft, Inc. Support Team.

We're happy to inform you that Ricksoft's WBS Gantt-Chart is a tool that we believe that perfectly suits your needs.

With WBS Gantt-Chart for Jira, you can use Baselines as first row - estimate time and updated Start/Finish dates as second row - final time.

Please check WBS Gantt-Chart at our Atlassian's Marketplace webpage. We offer a 1-month free trial for your Jira Instance.

If you have any other questions or issues, don't hesitate an open up a support ticket at our Jira Support page. We will be glad to help you out.

We're looking forward to hearing from you.

Have a great day!

Cheers,
Gabriel