So, I have a Project which has a bucket of hours, that means I have for example 200 hours that any of my 4 developers can use. it doesn´t work like 50 for each as BD some times work more while on other days FD works more.
So, I need to estimate the Project on the parent Ticket and log my hours on the Sub task ticket.
how do i do it, and please don´t tell me its better to put the estimated hours in the sub task, if i wanted to do that I would have done.
Thank you
Hello,
You should use the Time Tracking panel to sum up sub task work to the parent level:
If you provide a value for the Original Estimate field (add Timetracking field to screens), you will se the panel in view issue screen.