I marked the epic done
All tasks in the epic are done
The epic burndown report lists all tasks done
The burndown chart shows 1.4w remaining and three more sprints
I cannot figure out what is wrong. The report should show done status.
Here's the documentation about the report: https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-epic-burndown-report/
A Task or Story may not be actually done if the resolution field value is still unresolved.