Hello all! Newbie here. I have a project with the following fields:
* due date (JIRA default)
* Start Date (custom field)
* Est. End Date (custom field)
I'd like my timeline view to reflect: Start Date -> Est. End Date
As far as I can tell, by default the timeline view uses Due Date as the "end date" in that view.
So my solutions are either:
1. Edit timeline settings to reflect the fields that I want to see
2. Build an automation that changes the "due date" field to match my custom "Est. End Date" field
Thoughts on best approach?
Hello @Robbie Williams
Welcome to the Atlassian community!
Just for clarity, can you confirm you are referring to the Timeline feature that is available in Jira Business/Work Management projects?
If so, be advised that it is not currently possible to customize which date fields are used in the Timeline (or the Calendar). You can vote on a change request for that here:
Confirmed that's what I'm asking about and :( for the news that it's not possible.