Done Stories Moving to next Sprint following sprint close

John Bolton March 29, 2021

Hello, when closing a sprint it asked if I want the incomplete stories to go the backlog or next sprint.  After closing the done stories were added to the next sprint cluttering the story board.  Is there a way to have the stories stay in a done state and move with the closed sprint?  Thank you,

2 answers

2 accepted

1 vote
Answer accepted
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 29, 2021

Hi John - Stories are only considered to be done if they are in the Final column of the board - regardless of the status.

1 vote
Answer accepted
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 29, 2021

Where does your "Done" status reside within the scrum board? When completing a sprint only those issues that are in the right-most column are consider truly done. Otherwise they will be moved to backlog/next sprint.