Does the linked tasks dates gets automatically updated when parent task date is changed

Anand Gupta
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 4, 2020

I have task 1 and 2 and I want task 2 to start only after task 1 is completed. If the date of task 1 gets shifted will task 2 start date will automatically changed?

1 answer

2 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 4, 2020

No.

A link is a simple record of connection between two issues.  It does not do anything other than show the human that there is some connection.

You can, of course, use the links for all sorts of things, but there is no off-the-shelf function for "update issue at the other end of a link".  You will need to do some coding or find an app that can do it.

If you were to choose Scriptrunner for this, you might find some of the scripts at https://library.adaptavist.com/search?page=1&products=jira&term=LINK are a good starting point for you.