Hi Community,
I'm using the auto-scheduler to work with my plan and I'm having issues to understand why my stories are not occupying the sprints capacity. Most of the sprints are showing currently 0 points allocated, however the stories seem booked over several sprints. I've got a story with 55 story points, therefore is booked over several sprints BUT SPRINTS SHOW EMPTY.
- 1 week sprintS
- I've got an average velocity range 15-30 for each sprint.
- The story MVP-44 with 55 story points.
- I've got all stories assigned to one single shared development team.
I kindly ask for help, the auto-scheduler doesn't make sense.