For below gadgets, the days Remaining in Sprint gadget always shows 7 days instead of actual remaining days:
Sprint Health
Sprint Burndown
NOTE: The sprint dates are correct, and the estimation field is valid — the issue isn't with the board or sprint configuration.
Hi @Abhilasha Singh,
These gadgets display working days. Weekends are excluded by default, based on the Working Days configuration of the Agile board.
Could you please provide some screenshots? Also, is your Scrum board in a team-managed project or a company-managed project?
Danut
Hello @Abhilasha Singh
The "days remaining" calculation comes strictly from your sprint dates and the board’s Working Days setup, not the estimation field how many people thinks 🤗
Check your configuration under More > Configure board > Working days to verify your active days and timezone, keeping in mind that gadgets count working days rather than calendar days.
Next, compare the gadget with your board's Burndown Chart report. If the report is right but the gadget is stuck on 7, it's just a dashboard glitch. try removing and re-adding it. If both are wrong, the issue is in your board settings.
A quick quirk to test: if you have all 7 days selected as working days, try temporarily switching to a standard 5-day week to see if it resets, as there have been known bugs with 7-day setups. If that doesn't fix it, go ahead let us know and we can get attention from support (alternatively your Admin can do that directly 😉)
Best,
Arkadiusz 🤠☀️