Time Tracking is currently ON.
The number of working hours per day is 9.
The number of working days per week is 5.
*************************************
I'm not sure that my logic matches what Jira is doing, but I get 9 days too
Your sprint is set to cover three weeks, as below. My x's represent the days you've said "non working day", and the numbers are a counter.
20 Mar Tue 1 21 Mar Wed 2 22 Mar Thu 3 23 Mar Fri non-working 24 Mar Sat non-working 25 Mar Sun 4 26 Mar Mon 5 27 Mar Tue 6 28 Mar Wed 7 29 Mar Thu 8 30 Mar Fri non-working 31 Mar Sat non-working 1 Apr Sun 9 2 Apr Mon 10
3 Apr Tue 11 4 Apr Wed 12 5 Apr Thu 13 6 Apr Fri non-working 7 Apr Sat non-working 8 Apr Sun 14 9 Apr Mon 15 Release
By my counting, you should therefore get 15 days.
However, your time-tracking says there are only 5 working days per week, so you need to remove 2 days per working week, which means you get 15 -6 = 9 days...
Thanks for your reply but
20 [1], 21[2], 22 [3], 25 [4], 26 [5], 27 [6], 28 [7], 29 [8], 1 [9], 2 [10], 3 [11], 4 [12], 5 [13], 8 [14], 9 [15]
20 [15], 21[14], 22 [13], 25 [12], 26 [11], 27 [10], 28 [9], 29 [8], 1 [7], 2 [6], 3 [5], 4 [4], 5 [3], 8 [2], 9 [1]
Although non wroking days calculated before 6 days
Today 26 / 3 / 2012 >>>> The counter on dashboard now {8} , the counter must be 26 [11] 11 Days
If you have answer for this issue please reply me
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm sorry, my formatting got all messed up when I posted the original. I've re-done it as a code block, which seems more clear.
I don't understand what you're asking now though. What I'm trying to point out is that you have told Jira that your sprint is 21 days long, with 6 non-working days, and 5 working days per week (i.e. 2 in 7 are also non-working). 21 - 6 - (3 * 2) = 9 days. Whatever order you do the two "2 days not working", you get 9 working days in the three weeks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, I understand that, but you've added a load of non-working days to that particular sprint, so it's cutting it down more.
You've got 21 days listed
You have set your working week to 5 days, which means you need to remove 2 in every 7 days, which, for 3 weeks, means 6 to remove.
You've set up non-working days = 6, so you need to subtract them.
That leaves 9 working days.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The number of working hours per day is 9.
The number of working days per week is 5.
2 non- working days + 5 working days = total 7 days our sprint 21 days = 3 weeks that's right ok until now
we start sprint 20/03/2012 and it ends 09/04/2012 we cancel 2 non- working days for every week so non- working days will be 6 days
20/3 [15], 21/3 [14], 22/3 [13], 25/3 [12], 26/3 [11], 27/3 [10], 28/3 [9], 29/3 [8], 1/4 [7], 2/4 [6], 3/4 [5], 4/4 [4], 5/4 [3], 8/4 [2], 9/4 [1]
Today 26 / 3 / 2012 >>>> The counter on dashboard now {8 Days Remaining} , the counter must be 26/3 [11 Days Remaining ]
How can change this number from 8 to 11?
Thanks for your replies and effort with me
I got the reason we calculated non-working days twice the one time in General Configuration under GreenHopper, the second time in General Configuration on project's level How can i remove non-working days in General Configuration on project's level , Jira replys
GreenHopper includes global non-working days, they can be modified below to meet specific project requirements. Note: Global non-working days can be modified by your JIRA Administrator. These dates will not be shown in your charts. All worklogs will be associated to the previous working day.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't understand what the confusion is - based on what you've got in Jira/Greenhopper, it's doing the right calculation, and I don't get why you keep saying it's wrong. It's probably me just not being able to grasp what I'm reading - could you explain why you are expecting non-working days to be included as working days?
You've got 5 working days per week.
Then you've got global non-working days (which you hadn't mentioned before),
Then you've duplicated that at a project level.
You need to remove the duplicated days to begin with (project administration level), and then talk to your admins about the global non-working days, as it sounds like they might be wrong.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I got it , i was supposed to change the number of working days per week from 5 to 7 in time tracking.
Many thanks for your replies and effort with me
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hmm lets see, from my count:
1 - March 26th
2 - March 27th
3 - March 28th
4 - MArch 29th
5 - April 2nd (March 30th is a non working day)
6 - April 3rd
7 - April 4th
8 - April 5th
9 - April 9th (Release date, April 6th is a non working day)
Sums to 9 days, The bigger question is how did you get 13 :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.