Hi all,
I have widgets showing completion rate of issues per sprint and milestone. However, in order to contextualise how much progress we would expect at this stage of the sprint/milestone, I would like to add a progress bar simply showing time elapsed between dates.
It doesn't even need to be dynamic, I can set the start and end dates of the sprint/milestone. The sprint health gadget shows the time elapsed and work complete for the sprint, but I cannot do the same for milestones, or any other set time periods.
I can do a countdown to a date, but I need the percentage of time elapsed to compare it to the completion rate. The burndown chart also provides a guideline, but again I need this information in percentage format.
E.g. say our completion rate is 21% for the milestone, but we are 33% through (10 days elapsed out of 30d milestone). It means we're not on track.