Can we customize JIRA wrt sprint?

Example: If for any particular sprint we decide to release 25 tickets,but after some one or two days we want to add some more tickets to same sprint with same time duration..so I want to know about list of new tickets added to the particular sprint...

1 answer

0 votes
Fabio Racobaldo _Catworkx_
Community Champion
May 26, 2023

Hi @Rajeshwari Chilshetty ,

this is a usual way. Adding more tickets means scope change of your sprint. You can have all information about scope change using Burdown Chart.

Fabio