Can we customize JIRA wrt sprint?
Example: If for any particular sprint we decide to release 25 tickets,but after some one or two days we want to add some more tickets to same sprint with same time duration..so I want to know about list of new tickets added to the particular sprint...
this is a usual way. Adding more tickets means scope change of your sprint. You can have all information about scope change using Burdown Chart.
Fabio