Hi,
I want to start using Cross Project Releases. I have 2 questions:
1. If we have several teams, and each team use a way of estimation, the velocity used in Release Burndown Chart will be incorrect.
I'll explain with an example:
With those inputs, is the velocity of the Release (90+20)/2=55SP?
So, Release Burndown Chart will predict that we'll finish in one more sprint, or is it based in the individual velocities and will say 2 sprints?
2. If a team is working in two releases, will Jira calculate a velocity per release per team?
I'll explain with an example:
With those inputs, Release Burndown Chart will predict that we'll finish in one sprint or two?
Thanks