×Could i change project from kanban project to scrum project in order to manage sprint ?
Projects are Kanban or Scrum, their boards are. You can create a new Scrum board associated with the project. This will allow you to have Sprints on that board.
Adding to the answer from @Derek Fields _RightStar_
What project type are you using: company-managed or team-managed? You may find that information at the lower-left of the page expanding area.
For a company-managed project, you may add another board to use Scrum, as described.
For a team-managed project, there is only one board. You may enable sprints instead from the project features:
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud, our FedRAMP Moderate offering, is coming soon! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register Now
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.