Hi All, I have configured Burndown chart in Agile report and using the below setting
Estimation Field - "Remaining Estimate".
Time unit - hours
Completed Work - Daily / Cumulative.
Now when I check the burndown, I see the completed work shows the remaining hrs that are not completed in the Closed tasks/Stories as opposed to Logged hrs. If you do not have any remaining estimates in the closed tasks the Completed work shows "0".
How can we fix this ? Is there any open ticket to look at this issue.
P.S. I cannot hide completed work from burndown chart and 0 completed work shows an incorrect picture.
Any suggestions?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.