If I want to complete the sprint but some sub-tasks are not completed . 

How can I set it if I want to complete sprint and move the remaining sub-tasks which are not complete to next sprint?

Thank you 

 

1 answer

1 accepted

2 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 18, 2024 edited

Hello @Dr_Win_ST 

Subtask cannot be moved to and from Sprints separately from their parent issue. You must set the parent issue to a not-done status so that the parent issue will move to the next sprint due to being incomplete. It will take all it's subtasks to the next sprint with it.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
atlassian, atlassian government cloud, fedramp, webinar, register for webinar, atlassian cloud webinar, fedramp moderate offering, work faster with cloud

Unlocking the future with Atlassian Government Cloud ☁️

Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.

Register Now
AUG Leaders

Atlassian Community Events