If I want to complete the sprint but some sub-tasks are not completed .
How can I set it if I want to complete sprint and move the remaining sub-tasks which are not complete to next sprint?
Thank you
Hello @Dr_Win_ST
Subtask cannot be moved to and from Sprints separately from their parent issue. You must set the parent issue to a not-done status so that the parent issue will move to the next sprint due to being incomplete. It will take all it's subtasks to the next sprint with it.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.