Hi. I'm using the timeline view to create my project tasks. I need the Start date and due date columns to be visible before the Gannt chart. I can't figure out how to add the columns.
Hello @Alpana Kalideen
You may recall from my previous response to you in your post from April 9, that it isn't possible to add columns to the Timeline view with the Standard Jira subscription Basic Timeline functionality.
More information on the basic Timeline feature available in Jira Standard can be found here:
The functionality does not include adding columns to display issue field data in the Timeline view.
That functionality is available in the (Advanced Roadmaps) Plans feature that is included with the Premium and Enterprise subscriptions.
Alternately you can consider acquiring a third party app from the Atlassian Marketplace that provide more functionality around the customization of timeline/gantt charts.