Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Closing story the burn down chart shows wrong behavior. Please respond.

anshu
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 18, 2019

Hi,

Following are the issue's we are facing, please help us.

ISSUE 1:

When we have a story A with story point=1 in previous sprint and when you carry forward (move to the next sprint) and observed in the current sprint the story point is 0.

ISSUE 2:

Observed the story when we close it, it shows "Issue reopened" and graph goes up.

Please respond to these issue's. Appreciate your help on this regard.

Thanks

Anshu.

  

2 answers

0 votes
easwar@strawberryboxmedia.com September 18, 2019

Adding to it, please check the following bug, when you close the bug, it is saying "Issue-re-opened", absolutely wrong.

Please reply ASAP.

IS-262

IS-271

IS-258

Thanks

Easwar.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 18, 2019

What exactly are you doing to the story when you "close it"?  Which graph is going "wrong", the one for the first sprint or the second?

easwar@strawberryboxmedia.com September 18, 2019

Hi, I'm Easwar , QA Lead.

Graph is going wrong for the current sprint. so, here is the thing,

1. Move the story-1 from sprint-A to sprint-B (which is current sprint)

2. When you close the story-1 , the graph goes up.

https://strawberryboxmedia.atlassian.net/secure/RapidBoard.jspa?rapidView=1&projectKey=IS&view=reporting&chart=burndownChart&sprint=4&estimate=field_customfield_10102

Thanks
Easwar.

easwar@strawberryboxmedia.com September 18, 2019

You can check the story IS-84.

Thanks

Easwar.

Suggest an answer

Log in or Sign up to answer