Close a Sprint send all my "done" tasks in the next one.

Céline Janssens
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 11, 2023

Hello,

At the end of a sprint, available with the plugin Scrum, I should close it.

Normally, all the open tasks are send to the next one. But not the "done" ones.

But since 2 or 3 weeks (sprint)  it seems that the status "Done" is not recognize as a "final" status anymore when closing a sprint. All my done tasks / story / bug, are automatically associated to the next sprint with the same status "done" ( highlighted in green and id striked )

 

I checked in the workflow and the status "done" is Green  and defined as a final status.

I recently added a second final status "Obsolete" , that could be the reason why it doens't work properly anymore, but in the workflow, nothing presume that we connot have 2 final status !

 

Do you have any clue ?

Capture d’écran 2023-07-11 à 10.04.41.pngCapture d’écran 2023-07-11 à 10.04.03.png

 

 

 

1 answer

0 votes
Trudy Claspill
Community Champion
July 11, 2023

Hello @Céline Janssens 

Welcome to the Atlassian community.

Please show us the screen that shows the mapping of Statuses to Columns.

Only the issues in the column farthest to the right will be considered "complete" when the sprint is closed. All issues in all other columns, regardless of their actual Status, are considered "incomplete" and will be moved to the Backlog or another sprint at your direction.

If you have multiple Statuses that you want to be considered "complete" at the end of the sprint, all those Statuses must be mapped to the column farthest to the right.