Unable to complete a sprint - getting the message:

Sprint cannot be completed as there are incomplete subtasks on the following issues

 

Understand that incomplete subtasks would prevent me from completing the sprint.

I have the administrative permission and created a customized column "Cancelled" in the board in which the incomplete subtasks belong.

Would it be possible to configure the sprint to complete both the Done and Cancelled issues/tasks/subtask?

Temporarily i have moved the entire parent issue to the next sprint.

Thank you.

1 answer

1 accepted

0 votes
Answer accepted
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 2, 2020

Hello Damien,

Welcome to Atlassian Community!

On next-gen projects, only the last column adds a resolution to tickets and in Jira tickets are considered closed by the resolution and not by the status. 

With that said, if the sub-tasks are not moved to the very last column on the board, it will not be considered as closed and the error message about closing the sprint will appear.

Currently, it's not possible to set a resolution on another column.

There is a feature request suggesting this improvement:

Please, click on vote and watch to receive updates about the feature.

Regards,
Angélica

Damien
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 5, 2020

Thank you @Angélica Luz

Like Angélica Luz likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events