Is it possible to reorder the display of the workflow transition steps in Jira Data Center? This is my current display:
To Do (initial status) (GRAY)
Move to In Progress -> IN PROGRESS (BLUE)
Move to In Testing -> IN TESTING (BLUE)
Move to Done -> DONE (GREEN)
Move to Backlog -> BACKLOG (GRAY)
Move to Implementation -> IMPLEMENTATION (BLUE)
I'd like to change the display order to Backlog, In Progress, Implementation, In Testing, and Done.
Regards - Steve Janvrin.
Hi Steven,
You can do that by adding a property to the transition for opsbar-sequence. Here is the guidance.