When viewing the scrum board of an active sprint, we're not seeing sub-tasks with a status of "To-Do".
This is the issue in the backlog, with subtasks:
These are the sub-tasks, there are several open to-do items, but they do not show up in the view above:
Hello Scott,
Sorry to hear you are facing a problem. Please, follow the checklist below to determine why the sub-task in the To-Do status are not appearing in your board:
1 - Double check if the sub-tasks are children of the mentioned Story (CD-1000)
2 - Navigate to Board settings > General > Check if the board filter is not excluding the "To do" status. In fact, run the board query and check if the sub-tasks in "To do" are returning:
3 - Navigate to Board settings > Columns > Check if there is a "To Do" status under the unmapped statuses (Most right column).
Let me know your results.
Hi Scott,
I see that your board is not displaying all the issues you would expect here. I have a few clarifying questions I hope will help us troubleshoot this.
If these don't clear up what is happening here, I would be interested learn more about the specific filter being used for this board (the JQL syntax could be a clue), as well as seeing any Quick Filters defined for that board that might be setup to exclude issues in that status from appearing on the board itself.
Cheers,
Andy