The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can't remove "board" element from backlog

Little Gidding
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 29, 2024

I just enabled the backlog feature and I am project admin. The backlog board shows the backlog and the main project board in two different elements (screenshot attached). How can I remove the "Board" section from the backlog?

 

jira snip.PNG

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Trudy P Claspill
Community Champion
May 29, 2024

Hello @Little Gidding 

Welcome to the Atlassian community.

Based on your screen image I believe you are working with a Team Managed project. You can confirm that by looking for the text at the bottom of the navigation panel on the left where it should say "team-managed".

With a Kanban board Backlog screen there will always be two sections to the list. The upper section reflects issue that have been moved from the Backlog list to appear on the Board view. In a Team Managed project in order to place an issue into the Board view you have to move the card on the Backlog screen from the Backlog list section to the Board list section.

You cannot remove that upper list section from the Backlog screen.