Dear community,
I would like to know if there is a way how to set the sprint report, so the closed subtasks created under issues will be shown in the report before the issue is closed.
Thank you for your answer.
Regards,
Ingrid Begalova
Hi, Ingrid
Estimates on sub-tasks are not included in the Sprint Report. (Only estimates on parent issues are included, as you can see in our Sprint report documentation.
This is an expected behavior since sub-tasks are not considered as valid issues for the Sprint report or the Velocity chart.
They only show up in the Burndown report when you select specific estimations.
Let me know if this clarifies!
Gabi
Atlassian Team
Hi Gabi,
thank you for your answer. What do you mean by specific estimations?
BR
Ingrid