Can I roll-up the date on Timeline of project management project?

Angkana Lapthamrong
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 19, 2025

I created a project management project and create epic, task and sub-task. I put the start and due date of sub-task. Can I roll-up date to task and epic?

3 answers

3 votes
Trudy Claspill
Community Champion
January 19, 2025

Hello @Angkana Lapthamrong 

Welcome to the Atlassian community.

You could use Automation Rules to role up the dates. I wrote an article about it here:

https://community.atlassian.com/t5/Jira-articles/Updating-dependent-task-s-dates-when-predecessor-task-date/ba-p/2816977

Your post tags indicate you are using a free Jira subscription. If that is true you are limited to 100 rule executions per month. In that case the automation rules solution may not be right for you. Refer to this page for information about how automation rule usage is calculated.

https://support.atlassian.com/cloud-automation/docs/how-is-my-usage-calculated/

0 votes
Rob Jenkins
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 25, 2025

Sorry this isn't the most helpful answer, but re-creating the project as a software development - kanban project is the only way I've found to make the roll up dates work..

Suggesting to use automation is a bad solution.  It feels like there is a setting I'm missing (I am also new at Jira) because some of the project templates roll up dates and others don't and I don't know why!  (there is no automation set up that I can see that would do it)

Trudy Claspill
Community Champion
March 25, 2025

Hello @Rob Jenkins 

Welcome to the Atlassian community.

If you want to explore why some projects appear to roll up dates and others don't, please start a new Question by clicking on the Ask a question button at the top of the Community screen. We would need more details to offer feedback on your scenario such as the Subscription type you have, the project types involved (obtained from the Type column on the View All Projects page under the Projects menu), and screen images showing examples where dates are rolled up and where they are not. 

0 votes
Mohanraj Thangamuthu
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 19, 2025

Hello, Good day. Roll-up dates are available only in the Jira plans timeline and not the project-specific timeline. If you are looking to copy dates from sub-task to task, we can explore automation for Jira option.