Can I extend the timeline further back in time?

Daniel Hallberg
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 12, 2025

The timeline of a project only goes back to 2024. There are tasks way older then that. Can I extend the timeline to show me tasks over a longer timeframe including several years ago?

1 answer

1 accepted

8 votes
Answer accepted
Trudy Claspill
Community Champion
January 12, 2025

Hello @Daniel Hallberg 

Welcome to the Atlassian community.

For the basic Timeline, no, you cannot.

There is a change request about it to which you can add your vote.

https://jira.atlassian.com/browse/JSWCLOUD-17799

I am still looking for information about the Timeline view available for Plans in Jira Cloud Premium.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events