August 8, 2022

AvHi there,

Very new to all the analytics of JIRA but I was curious about something.

 

I would like to know for each assignee , on average, how many of their tasks to they complete by the end of a sprint.

 

So as an example:

SPRINT 1

Assignee 1: 2/3 tickets complete

Assignee 2: 1/1 tickets complete

Assignee 4: 1/2 tickets complete

 

SPRINT 2

Assignee 1: 1/2 tickets complete

Assignee 2: 0/0 tickets complete

Assignee 3: 3/4 tickets complete

Assignee 4: 2/2 tickets complete

 

 

RESULT

 

Assignee   Avg. Tickets Completed Per Sprint

             1                                                       .58

             2                                                     1.00

             3                                                       .75

             4                                                       .75

 

 

 

Can this be done at the ticket and subtask level?

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 8, 2022

Hi @John Thomas -- Welcome to the Atlassian Community!

First, reporting like that is not supported with out-of-the-box features of Jira Cloud.  Specifically, built-in reporting and searches are on issue data; they cannot find the absence of information, such as "0 found..."

Next, what problem are you trying to solve be doing this?  You note sprints, which seems to imply the team is using the Scrum Framework.  And if so, such teams deliver value together, so measuring individual performance this way could lead to unintended consequences.

Kind regards,
Bill

John Thomas
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 10, 2022

I truly am asking for myself. I would like to know on average how many of my tickets do I complete per sprint. The case where 0 is found is thereby fine to ignore

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 10, 2022

Thanks for clarifying, John.

You could create a filter for your items, save it, and subscribe so it sends an email just before the sprint closes.  For example, let's assume you have a two week sprint, this might help:

project = myProjectName AND assignee WAS currentUser() DURING ( startOfWeek(-2), endOfWeek(-1) ) AND sprint IN openSprints()

If you need to do this for other sprints, you could adjust the dates and sprint(s) included, and perhaps make a dashboard showing the last-N sprints.

If you need something more sophisticated on the reporting, I recommend using the Excel (or Google Sheets) addins to build your own reporting or to investigate the Atlassian marketplace for reporting tools.