Burndown chart is not working

AGarg
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 27, 2024

burndown chart.jpeg

The chart is not working and not able to identify what the problem is? as it is a copied project and the other project seems to be working fine. Also, the board is configured accurately, Done column set to resolution, all the tags in it right column. What am I missing here?

1 answer

0 votes
AGarg
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 27, 2024

Found the problem! The start date of sprint mentioned was wrong. 