I have created a small program in the BigPicture and created Gantt with links between tasks ("has to be done after) and baseline.
Now, a new and urgent issue has created and must be done in the middle.
For example:
The order of the original program was:
Task A ---> Task B ----> Task C
Now:
Task D was created and must be done in the middle of Task B (Task B was already started).
Due to that, the rest of Task B & whole Task C will be delayed.
How can I split Task B in the middle so I could represent the change and the delay?
(There is only one resource).
Can I show something like this?
Task A ---> Task B (part1) ----> Task D ---> Task B (part2) ----> Task C
Hi Yakir
I recreated your scenario, as pictured.
The BU-16 task is "in progress".
Created your Task D, it's BU-44 in the screenshot below.
Cloned the BU-16, so that BU-46 was born.
Recreated the end-to-start links between the tasks.
Deleted the baseline of BU-16, so that the baseline of BU-46 stands for the overall delay.
Yes, your scenario is doable to me.