HI,
In Big Picture using resource module, if you assign a person to a task with 50% availability, task is under-allocated. How do you make task is fully resourced using the same person ?
I tried extending task duration to compensate by doubling the task duration, but the original estimate just increases as well so task under allocation is never fixed.
Thanks
Simon