I have two questions:
Question #1: How to develop critical paths in both Jira Plans and Big Picture? I have created strong dependencies between tasks, but I am unable to create critical paths in either plug-in.
Question #2: Utilization of Big Picture as a portfolio management tool, is it a possibility?
Hi James,
1. I don't think you can work with critical path in Advanced roadmaps, but in Big Picture you can display it by using this button :
2. Big Picture Enterprise (paid app) can be used as a portfolio management tool, but in its free version it will be limited. For example, I don't think you can consolidate data from your various boxes at portfolio level (parent box).