Hi all,
I am looking to create an automation rule to calculate Start and end time for an issue based on the earliest start and latest end from linked issues
Issue 1 -> relates to Issue 2 ( Start 1-Aug-24, End 20-Aug-24)
Issue 1 -> relates to Issue 3 ( Start 1-Jul-24, End 10-Aug-24)
From the above example, I want to set Issue1 start to 1-Jul-24 and end to 20-Aug-24